The new sanctuary continues to advance on its completion date in six to eight weeks if everything lines up correctly. Still many tasks to complete but it is looking great to this point. The operable windows are in, the new speakers are in place overhead, some of the theatrical lighting is in place, the audio wires are being pulled into place.
We’ve heard from SoCal Edison that they can make the new connection live on this Saturday and they will have to shut off all electricity from 9 am to 1:30 pm on Saturday only.

The new entrances on Mesa Verde Drive are beautiful and code compliant.
Photo credits to Barbara M.

Craig Spery is the chair of the sanctuary planning and construction committee