We anticipate that installation of the roof trusses will be getting underway this week. The remaining fourth exterior wall will be installed after the roof trusses are in place. Meanwhile the electrician is placing conduit for the future Internet connection to the sanctuary. According to the contractor we are still ahead of schedule by two weeks.
Craig Spery is the chair of the sanctuary planning and construction committee