Sanctuary Construction Update – Week #10

Sanctuary Construction Update – Week #10

The framing of the walls for the new sanctuary continues this week with three of the four exterior walls completed. The roof trusses have been delivered to the site and will start to be installed next week. The remaining fourth exterior wall will be installed after the roof trusses are completed. The canopy in front of the main front door (the Nanawall) has been framed and it indicates how much shade will be provided during the day. According to the contractor we are still ahead of schedule by two weeks.

Want to catch the construction action in real time? Check out the Live Sanctuary Cam here!


Craig Spery is the chair of the sanctuary planning and construction committee