The work continues at a rapid clip. The interior ceiling of the sanctuary has been painted black before the suspended ceiling is installed and the three operable skylights have been placed and tested. Drywall continues to be installed on the walls and part of the ceiling. The creation of the raised platform for the pulpit and choir areas has begun. The substructure will be eventually covered in oak. Preparations for the application of stucco on the exterior walls continues and the stucco will be applied soon, perhaps next week.

Craig Spery is the chair of the sanctuary planning and construction committee