The roof work continues with new openings being made for the skylights and the HVAC (heating, ventilation and air conditioning) system. An additional opening has been made for the roof hatch for future access. Interior walls are beginning to be framed.

Other completed work includes placing conduit for electric and communications and installing the drainage pipes for the storm water system.

Want to catch the construction action in real time? Check out the Live Sanctuary Cam!


Craig Spery is the chair of the sanctuary planning and construction committee